| Province | Subbasin | % |
|---|---|---|
| Basinwide | - | 100.00% |
| Previous: | Next: |
|---|---|
| 20620 REL 24: 2006-006-00 EXP HABITAT EVALUATION PROJECT |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Paul (CBFWF) Ashley | Columbia Basin Fish and Wildlife Foundation | Yes | Technical Contact | lonepinebutte@comcast.net.old | (509) 979-2866 |
| Jann Eckman | Columbia Basin Fish and Wildlife Foundation | Yes | Contract Manager | jann.eckman@cbfwa.org | (503) 229-0191 |
| Sandra Fife | Bonneville Power Administration | Yes | COR | safife@bpa.gov | (503) 230-3678 |
| Tom (CBFWA) Iverson | Columbia Basin Fish and Wildlife Foundation | Yes | Supervisor | tom.iverson@cbfwa.org | (503) 229-0191 |
| Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
| Donald Rose | Bonneville Power Administration | Yes | Env. Compliance Lead | dlrose@bpa.gov | (503) 230-3796 |
| Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Attach Progress Report in Pisces | A: 132. Submit Progress Report for the period 10/01/2010 through 9/30/2011 | 02/12/2012 | 02/03/2012 | |
| HEP schedule for up-coming field season | B: 174. Produce HEP schedule for FY 2012 field season and master plan for out years | 05/04/2012 | 05/04/2012 | |
| Deliverable: Receipt of environmental compliance clearance from BPA | C: 165. Environmental compliance documentation | 01/01/2012 | 12/31/2011 | |
| All FY09/10/11 HEP reports submitted to BPA and CBFWA | D: 87. Compile and report HEP results to CBFWA and BPA | 06/01/2012 | ||
| Habitat suitability and habitat units assessed | E: 162. Assess HEP field data | 05/31/2012 | 05/31/2012 | |
| All planned FY12 HEP surveys complete | F: 157. Conduct FY12 HEP surveys | 09/30/2012 | 09/25/2012 | |
| Pilot study for baseline documentation and enforcement monitoring | G: 115. Pilot study for baseline documentation and enforcement monitoring | 09/30/2012 | 09/14/2012 | |
| All administrative requirements for FY12 contract | I: 119. Perform administrative duties | 09/30/2012 | 09/25/2012 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 132 | Submit Progress Report for the period 10/01/2010 through 9/30/2011 | 10/01/2011 | ||||||
| B | 174 | Produce HEP schedule for FY 2012 field season and master plan for out years | 10/01/2011 | ||||||
| C | 165 | Environmental compliance documentation | 10/01/2011 | ||||||
| D | 87 | Compile and report HEP results to CBFWA and BPA | 10/01/2011 | ||||||
| E | 162 | Assess HEP field data | 10/01/2011 | ||||||
| F | 157 | Conduct FY12 HEP surveys | 10/01/2011 | ||||||
| G | 115 | Pilot study for baseline documentation and enforcement monitoring | 10/01/2011 | ||||||
| H | 185 | Periodic Status Reports for BPA | 10/01/2011 | ||||||
| I | 119 | Perform administrative duties | 10/01/2011 |